Project No: CRP 3274

Project Design Engineer:  Nathan Thompson P.E.

Project Timeline: 2021

Project Description: Enhance stop signs at various locations throughout Spokane County.  Enhancements may include replacing old stop signs to increase reflectivity, installing larger stop signs, or adding red reflective strips to stop sign posts.

Project Update: 5/1/2021.   Signing materials were ordered in January.  Material delivery has been delayed due to supplier issues.  Due to material delays, the project is anticipated to begin June 2021.

8/16/2021. Construction 75% complete.

12/16/2021.   Construction complete December 2021

Project Funding: Federal Funds Awarded:  $ 387,818.00   County Funds (Local Match): $0.00,   Total project budget: $387,818.00