Appleway Ave. Reconstruction - Rocky Hill Road to Spokane Bridge Road
Project No: C3281
Project Manager: Mick Flugel
Project Timeline: Advertise late July 2021, Construction after Labor Day 2021
Update January 2022: Project completed.
Project Description: This project will remove pavement in travel lanes, place 4” of HMA in the existing lane width and 2” of HMA over the entire road section for a total depth of 6” of HMA over the travel lanes. Existing guardrail will be replaced.
Project Funding: County Funds