SPOKANE COUNTY PUBLIC WORKS
ROAD CONSTRUCTION AND MAINTENANCE
February 24 to March 3, 2023
www.spokanecounty.org/publicworks
http://www.spokanecounty.org/3828/Weekly-Travel-Impacts-Map
ROAD CONSTRUCTION
Euclid Road Bridge No. 1508
Removing and constructing new bridge and road approaches; including asphalt pavement, signing, striping, erosion control, filter drain, installing beam guardrail, and miscellaneous structures. Dates: March 1-September 30, 2023.
Euclid Rd: from Bridge #1508 over Burlington Northern Santa Fe tracks to Lyons Rd. Road Closed: Bridge is closed. Use Detour.
West Terrace Stormwater Project
This contract provides for the improvement of Hayford Road and Richland Road by construction of a storm sewer system. The project includes catch basin, corrugated metal pipe, drop inlet, cutoff wall/pipe anchors, unsuitable pipe foundation, dewatering, and paving. Completed: July 1, 2023. Completed: July 1, 2023.
Richland Rd: from Hayford Rd to Hayford Rd
Lane restrictions (both directions, all lanes). Watch for flaggers
Hayford Rd: from Westbow Rd to Richland Rd
Road CLOSED intersection of Westbow and Hayford. Not closed near Richland.
PRIVATE CONTRACTOR WORK BY PERMIT
UNICEP Sampling and Monitoring Project
Project includes the installation of a new 10-inches line to replace the existing manhole. Completed: March 4, 2023.
Contractor: Inland Infrastructure – (509) 514-0639.
Thorpe Rd: from Grove Rd to Carnation Rd
Lane closed (both directions, all lanes): Shifting lane closure on W Thorpe Rd to the West of S Grove Rd intersection.
Vault Work
Project will access existing vaults, bore, trench and upgrade. Completed: March 3, 2023.
Contractor: North Sky Communications – (208) 661-6344.
57th Ave: from Stone St to Crestline St
Lane closed (both directions, all lanes): E 57th Ave. at S. Stone St. WB Lane E. 57th Ave., east of S. Stone St. Right Lane closure WB. Center Lane closure EB. E. 57th Ave. at S. Crestline St. Right Lane closure WB. Left lane closure EB. Crosswalk accessible E 57th Ave at S. Stone St. Right lane closure EB.
Installation of Water Main
Crew will install valve for main crossing the freeway on W Westbow Blvd approximately 20-feet west of the Thorpe intersection. Completed: March 2, 2023.
Contractor: City of Spokane Water Dept. – (509) 625-7843
Westbow Bv: from Thorpe Rd to Spotted Rd
Road Closed: Road Closure on W Westbow & W Thorpe
-###-
www.spokanecounty.org/publicworks
The mission of Spokane County Public Works is to provide our citizens and the traveling public with safe and maintained roads, bridges and stormwater facilities through efficient and quality Operations, Construction, Engineering and Planning services.