Posted on: May 1, 2023

[ARCHIVED] Road construction and maintenance update for May 1-5, 2023.

 

SPOKANE COUNTY PUBLIC WORKS                          

ROAD CONSTRUCTION AND MAINTENANCE 

May 1 to May 5, 2023

www.spokanecounty.org/publicworks 

http://www.spokanecounty.org/3828/Weekly-Travel-Impacts-Map

 


ROAD CONSTRUCTION


Bigelow Gulch Mitigation – Start Date TBD
Improvement of the Bigelow Gulch Road Offsite Mitigation site located along Minnie Creek near Fish Lake Regional Park by clearing and grubbing, temporary irrigation, grading, planting and other work.


Brooks Road Reconstruction – Start Date TBD
Improvement of Brooks Road by reconstruction and widening by clearing and grubbing, roadway excavation, embankment compaction, cement spreading, crushed surfacing, hot mix asphalt, contractor designed underground structure, beam guardrail and other work. Completed: April 28, 2023.


Euclid Road Bridge No. 1508 
Removing and constructing new bridge and road approaches; including asphalt pavement, signing, striping, erosion control, filter drain, installing beam guardrail, and miscellaneous structures. Completed: September 30, 2023.


Euclid Rd: from Bridge #1508 over Burlington Northern Santa Fe tracks to Lyons Rd. Road Closed: Bridge is closed. Use Detour.


Lincoln Road and Sewer
Project includes improvements to Lincoln Road from Market Street to Crestline Street by replacement of the entire roadway, widening vehicle travel lanes, the addition of stormwater management infrastructure, and moving pedestrians to new locations. 
https://www.spokanecounty.org/5214/Lincoln-Road-and-Sewer. Completed: October 31, 2023. 


Lincoln Rd: from Market St to Crestline St
Flaggers may be present (both directions, all lanes): Flaggers may be present along Lincoln Rd at N Altamont: N Crestline: N Regal: N Smith & N Market.


West Terrace Stormwater Project
This project provides for the improvement of Hayford Road and Richland Road with the construction of a storm sewer system. The project includes a catch basin, corrugated metal pipe, drop inlet, cutoff wall/pipe anchors, unsuitable pipe foundation, dewatering, and paving. Completed: July 1, 2023. Completed: July 1, 2023.


Richland Rd: from Hayford Rd to Hayford Rd
Lane restrictions (both directions, all lanes). Watch for flaggers

Hayford Rd: from Westbow Rd to Richland Rd
Road CLOSED intersection of Westbow and Hayford. Not closed near Richland.


PRIVATE CONTRACTOR WORK BY PERMIT.


Carla Peperzak Middle School
Crosswalk modifications and parking lot construction. Completed: August 15, 2023. Contact: Garco Construction, Frank Hoerner – (509) 934-0030


Altamont St: from 63rd Av to South End to 63rd Av
Road closed: S Altamont Road closure


Farwell Road Multifamily Apartments
MGM Grand – (509) 370-2802 crew working in the right=of-way at E. Farwell Road between Mayfair and Ruby. Project includes excavation, fire hydrant, sewer/water services and repair, asphalt paving and road closure. Completed: May 3, 2023.   


Farwell Rd: from Mayfair Rd to Ruby Rd
Road CLOSED: Road closed at E Farwell between Ruby and Mayfair


Mead Works
Continental Contractors: (509) 724-3179. Water & Sewer Tie In at Mellon Parkway and Farwell Rd. eastbound. Completed: August 18, 2023.


Farwell Rd: from US-2 (Newport Hy) to Shady Slope Rd
Road CLOSED: Mellon Parkway Road Closure & Farwell Eastbound


Sewer Construction 
Poul Construction: (509) 979-5872. Sewer connection project. Completed: April 24, 2023.
 

Thorpe Rd: from Assembly Rd to Grove Rd
Road CLOSED: Thorpe closed from Assembly to Grove


MAINTENANCE


Asphalt Overlay
Apply asphalt over large areas of roadway for preservation.
Spokane County Public Works: Maintenance: (509) 477-3600


Perry Rd: from Burk Rd to Half Moon Rd
Lane restrictions (both directions, all lanes): Flaggers will be present.
05/01/2023 - 05/02/2023


Andrus Rd: from Chalet Dr to Jensen Rd
Lane restrictions (both directions, all lanes): Flaggers will be present.
05/03/2023 - 05/03/2023


Cheney-Spokane Rd: from Marshall Av to Sherman Rd
Lane restrictions (both directions, all lanes): Flaggers will be present.
05/04/2023 - 05/04/2023


Washington Rd: from Gardner Rd to Short Rd
Lane restrictions (both directions, all lanes): Flaggers will be present.

05/04/2023 - 05/08/2023


Crack Sealing
Application of a flexible sealant in cracks to prevent further break up on asphalt roads.
Spokane County Public Works: Maintenance: (509) 477-3600


Grading gravel roads
Grading of gravel roads to cut out washboards for a smooth traveling surface.


Pot Hole Patching
Patching holes where needed throughout Spokane County.


Street Sweeping
Cleaning of paved roads with street sweepers or kick brooms.


Weed Spray
Yearly Weed Spray on County Roads

-###-

www.spokanecounty.org/publicworks 

 

The mission of Spokane County Public Works is to provide our citizens and the traveling public with safe and maintained roads, bridges and stormwater facilities through efficient and quality Operations, Construction, Engineering and Planning service