Spokane County Logo

News Release


Martha Lou Wheatley-Billeter, MPA

Public Works Information and Outreach Manager

Office: 509-477-7195

mwheatleybilleter@spokanecounty.org

Road Construction and Maintenance Update

April 21-28, 2023

  
SPOKANE COUNTY, April 21, 2023 – News release text.


ROAD CONSTRUCTION


Bigelow Gulch Mitigation
Improvement of the Bigelow Gulch Road Offsite Mitigation site located along Minnie Creek near Fish Lake Regional Park by clearing and grubbing, temporary irrigation, grading, planting and other work. Completed: April 28, 2023.


Brooks Road Reconstruction
 
Improvement of Brooks Road by reconstruction and widening by clearing and grubbing, roadway excavation, embankment compaction, cement spreading, crushed surfacing, hot mix asphalt, contractor designed underground structure, beam guardrail and other work. Completed: April 28, 2023.

Euclid Road Bridge No. 1508 
 
Removing and constructing new bridge and road approaches; including asphalt pavement, signing, striping, erosion control, filter drain, installing beam guardrail, and miscellaneous structures. Dates: March 1-September 30, 2023.

Euclid Rd: from Bridge #1508 over Burlington Northern Santa Fe tracks to Lyons Rd. Road Closed: Bridge is closed. Use Detour.

Lincoln Road and Sewer
 Project includes improvements to Lincoln Road from Market Street to Crestline Street by replacement of the entire roadway, widening vehicle travel lanes, the addition of stormwater management infrastructure, and moving pedestrians to new locations. 
https://www.spokanecounty.org/5214/Lincoln-Road-and-Sewer. Completed: October 31, 2023. 


               Lincoln Rd: from Market St to Crestline St
               Flaggers may be present (both directions, all lanes): Flaggers may be present along                  Lincoln Rd at N Altamont: N Crestline: N Regal: N Smith & N Market.


West Terrace Stormwater Project
This project provides for the improvement of Hayford Road and Richland Road with the construction of a storm sewer system. The project includes a catch basin, corrugated metal pipe, drop inlet, cutoff wall/pipe anchors, unsuitable pipe foundation, dewatering, and paving. Completed: July 1, 2023. Completed: July 1, 2023.


                Richland Rd: from Hayford Rd to Hayford Rd
                Lane restrictions (both directions, all lanes). Watch for flaggers


                 Hayford Rd: from Westbow Rd to Richland Rd
                 Road CLOSED intersection of Westbow and Hayford. Not closed near Richland.


PRIVATE CONTRACTOR WORK BY PERMIT


47 South Apartments
MJM Grand - (509) 370-2802 crew doing misc. work in the right-of-way from Garden Springs to S. Windsor. Project includes excavation, utilities, asphalt paving and road closure. Completed: April 26, 2023.


                 
Abbott Rd: from Garden Springs Rd to Windsor Rd
                 
Road CLOSED: Abbott Rd closure between Garden Springs & Windsor
 

Carla Peperzak Middle School
Crosswalk modifications and parking lot construction. Completed: August 15, 2023. Contact: Garco Construction, Frank Hoerner – (509) 934-0030


                Altamont St: from 63rd Av to South End to 63rd Av
                
Road closed: S Altamont Road closure


Farwell Road Multifamily Apartments
MGM Grand – (509) 370-2802 crew working in the right=of-way at E. Farwell Road between Mayfair and Ruby. Project includes excavation, fire hydrant, sewer/water services and repair, asphalt paving and road closure. Completed: April 28, 2023.   


                 
Farwell Rd: from Ruby Rd to Mayfair Rd
                 
Road CLOSED: Road closed at E Farwell between Ruby and Mayfair


Mead Works
Continental Contractors: (509) 724-3179. Water & Sewer Tie In at Mellon Parkway and Farwell Rd. eastbound. Completed: August 18, 2023.


                 
Farwell Rd: from US-2 (Newport Hy) to Shady Slope Rd
                 
Road CLOSED: Mellon Parkway Road Closure & Farwell Eastbound


Sewer Construction 
Poul Construction: (509) 979-5872. Sewer connection project. Completed: April 24, 2023.
 

                Thorpe Rd: from Assembly Rd to Grove Rd
                Road CLOSED: Thorpe closed from Assembly to Grove


MAINTENANCE

Crews are sweeping and grading (depending on road conditions) throughout Spokane County.

-###-

www.spokanecounty.org/publicworks 

 

The mission of Spokane County Public Works is to provide our citizens and the traveling public with safe and maintained roads, bridges and stormwater facilities through efficient and quality Operations, Construction, Engineering and Planning services.

About Spokane County
Spokane County government serves more than 500,000 citizens and 13 municipal jurisdictions, making it the fourth largest county in the State of Washington. For more information, visit www.spokanecounty.org, like us on Facebook, or follow us on Twitter.


-# # #-

Share on Facebook
Share on Twitter
Share via Email

Copyright 2021 Spokane County. All Rights Reserved.
1116 W Broadway, Spokane WA, 99260

Powered by
CivicSend - A product of CivicPlus