Spokane County Road Construction Update
May 19-26, 2017
SPOKANE COUNTY, May 19, 2017 – Road crews will be busy thanks to a stretch of nice weather that is forecast for next week.
CONSTRUCTION
Country Homes Blvd (from Wall to Division)
Swale Construction work on the median islands, landscaping & irrigation adjustments.
Spokane County Public Works: (509) 477-3600
Country Homes Bv : from Wall St to US-395 (Division St)
Lane Closed (Both Directions, Lane Restrictions): Working on plant establishment, swales.
04/17/2017 - 05/31/2017
Market Street-Houston to Lincoln
Installing curb, sidewalk, ramps, catch basins, drywells, swales, sewer pipe, repair & replace asphalt.
Spokane County Public Works: (509) 477-3600
Market St : from Houston Av to Lincoln Rd
Lane Closed (Both Directions, All Lanes): Lane Restrictions, Expect delays
05/29/2017 - 07/31/2017
Monroe Street Swales (Country Homes Blvd-Cedar & Excel)
Repair and repave asphalt and install curb, sidewalk, catch basins, drywells, sewer pipe. Project starting on Monroe @ Wall working in the shoulders. Some delays when entering the roadway. Project on Country Homes @ Cedar will start following week.
Spokane County Public Works: (509) 477-3600
http://www.spokanecounty.org/3664/Monroe-St-Preservation-Improvements
Country Homes Bv : from Cedar Rd to Excell Dr
Lane Closed (Both Directions, Shoulder): Shoulder closed, Flaggers may be present when a lane closure is needed, expect delays.
05/17/2017 - 06/30/2017
Ritchey Road Bridge
Removal of the existing bridge & replace with new structure
Spokane County Public Works: (509) 477-3600
5/19/2017
Ritchey Rd : from Bannock Av to US-2
Road Closed: Road closed for bridge replacement
03/29/2017 - 08/31/2017
For more information: www.spokanecounty.org/publicworks